Third week

After having a good dry first two weeks, we have had a rather wet third week which has held us up a little, mainly turfing the new bunkers and rough areas. As you can see from the pictures, we have really achieved a lot in 3 weeks, with the sleeper wall on the 7th hole finished and bunkers on 8th and 9th ready for turf.

Weather depending, we hope to have by christmas the 7th and 9th all complete and all the bunkering finished on 8th. The lake edge on 8th hole will take a few more weeks, as we will start the new edging tomorrow.