Praying for no more rain

 

Now christmas is over and contractors are back on site, the weather has really been against us. Luckily ATBone worked through the christmas period to get the lake edges finished, which i think you will agree look really good. We are just waiting for the areas to dry out so we can then top soil and turf 7th & 8th. A pipe has been added to the 8th lake that runs into the small stream between 1st & 8th. This has been put in, to stop the water coming over the sleeper wall which it has done most years. There is only a small fall from the lake to the stream, but this should be adequate enough for what we want to acheive.

Profusion are finishing prepping the 9th, ready for turf next week. We have decided that the 10th is to wet to start work on, so we are starting shaping the bunkers on 1st & 18th this week. Hopefully by next week we should have 7th, 8th, 9th, 1st & 18th starting to look prepped and ready for turf to finish.

Pathways are on schedule with 7th, 8th & 9th all concreted with the 10th hopefully finished next week.

The irrigation has started on the 9th with cable and pipe being ploughed into the ground with minimal disruption. They will then be moving 0nto 7th & 8th, then to the 1st & 18th. They have a lot to install with over 1200 sprinkler heads to go in.

 

 

Leave a comment