We have been very lucky to have a very dry week last week, which has made us really crack on and back on schedule. Profusion have finished shaping all the bunkers with just drainage, liner and turfing to be done. They still have 4 tees to construct on 1st,8th, 12th and 17th. We are also altering the 11th green this week and putting a slight mound in the middle of the green at the back. We will be stripping part of the green and raising up in conjuction with the mound at the back of the green, to add more thought to your shot in.
Pathways have been finished with just soiling up of the edges and raising of areas to be done.
Irrigation only have 2 more fairways and 1 green left to pipe, but still have a lot of wiring and finishing to be done on all 9 holes.