We are now 4 weeks into our second year of the project and weather has been on our side for the first 3 weeks, but the past week has been horrendous. We started on the 2nd hole and will be then going to 6th,13th,16th,3rd,14th,15th,4th,5th. Again we will be re-shaping and moving all the bunkers, installing new irrigation and installing new concrete pathways.
Pathways team have really pushed on and have dug out and stoned 4 holes, with three concreted and finished already. A few rain showers have stopped us from concreting more holes but hopefully we will have the dryest winter on record this year!!!!!!
Irrigation have pulled in all the main lines piping for the 9 holes and have completed installing all irrigation from tee to green on the 2nd and 13th hole, and will be starting 6th hole today. Both irrigation and pathways are ahead of schedule.
Profusion are on schedule and have shaped all the new bunkers on the 2nd and 6th holes. New tees have been constructed on both holes with soiling and root zone still to be finished. Drainage has been installed in all these bunkers with top soil and turfing of these bunkers starting next week, so both holes should be taking shape for you to see.