We are up to week 7 and are ahead of schedule at this point. The contractors will be finishing for christmas on Tuesday 20th December, with irrigation being completed on 6 holes. All piping, sprinklers and valve boxes are all complete in these 6 holes, with just 15th, 4th and 5th to finish. The weather has played a great part in being so far ahead at this point. unfortunately, the irrigation cannot carry any work untill Profusion have shaped more holes.
Profusion have shaped all the new bunkers on 2nd, 3rd, 6th, 13th, 14th and 16th and installed drainage to them. They still have a lot of work to do with liner, top-soil and turfing to carry out. The course will really start to take shape at the end of January when holes will start to be finished and contours of the bunkers will really be able to be seen.
Pathways are really looking good and am very pleased with their work this year. They will be laying mainly concrete this week and hope to get the 4th green to 5th tee finished. The paths that will have been finished with concrete by the end of this week are 2nd, 4th, 5th, 6th, 14th and 15th.