The weather has really been on our side the past couple of weeks, which has meant great progress for irrigation and pathways.
Irrigation have completed instilation of all pipe work and sprinkler heads, into 4 holes. The ground conditions have been perfect for pulling pipe in, with very little mess being made. We are hoping to have only 3 holes left to install irrigation after christmas.
Pathways are also way ahead of schedule with 60% of the work done already. The weather has allowed them to concrete most days but the frost over the past few, has held them up a little.
Profusion have shaped bunkers on 4 holes and installed drainage and liner to them, but finishing off and turfing will not take place untill January. We have shaped a big grass run off into the greenside bunker on 13th, which spreads across the front half of the green. This is a change to the plans which I felt was needed for the second shot in. It is hard to see how good this looks from the photo, but i really think this will improve (make harder) the hole.
Feel free to have a walk around the holes we are working on, to see how they are taking shape. I am always about if you need to discuss any of the changes or an update on progress.