Firstly i must apologies for not putting any info on here over the christmas period. There was no turf laid, so it was really hard to see the bunker shapes with the camera. We are now 11 weeks into phase 2 and have had some great weather conditions, to carry out the works.
Irrigation will be finished putting in all the pipe and sprinklers by Friday. All that will be left to do is finishing wiring and cable joint. This is 8 weeks ahead of schedule which is great, so good time for the ground to settle, where pipe has been pulled in.
Pathways are just over 75% finished, which again is down to the weather conditions. We hope to have the pathways finished 6 weeks ahead of schedule.
Profusion have shaped 7 holes with only 4th & 15th left to do. 5 holes have been lined and drained ready for soiling and revetted turf. The 2nd & 6th holes will be finished this week and are really looking good.