Monthly Archives: February 2017

Didn’t need the rain

The past week has been horrendous with all the rain we received. We could not do any shaping or top soiling to any holes but we did get bunkers lined and drained. The 2nd, 6th and 14th are all completed with the 3rd, 16th and 13th just needing turf. Over the next 2 weeks we hope to have just the 4th and 5th to complete.

Irrigation have finished installing pipe’s and irrigation heads, with only inputting to be down on the computer system. The new system has been flushed through and is ready to be primed for the new season ahead.

Pathways are nearly finished with only the 16th to do. One more weeks work and these contractors will be moving out.